POWER STATION 5 BLOCK 4

Leaf Icon
Aeriel view of Alba’s Power Station 5 Block 4

Enhancing Efficiency and Sustainability

Project Overview

Power Station 5 Block 4, featuring a 680.9 MW generating capacity at 25°C and 54.6% efficiency, was successfully commissioned and formally handed over to Alba on December 22, 2024. This advanced block comprises a Mitsubishi M701JAC gas turbine, a Hitachi steam turbine, an SPX-Air Cooled Condenser, and a XIZI HRSG, along with supporting infrastructure.

tech
Technology

The M701JAC gas turbine represents cutting-edge technology, delivering high temperature, high efficiency, and low NOx emissions.

capacity
Capacity & Efficiency Gains
  • The project has expanded the Power Station 5 Complex’s nameplate capacity from 1.8 GW to 2.4 GW. Overall power station efficiency has increased:
    • From 48.70% to 50.99% during summer.
    • From 50.02% to 52.25% during winter.
  • Achieved LHV efficiencies of 60.80% (winter) and 59.14% (summer), with NOx emissions within regulatory limits.
Sustainability
Sustainability Impact

Block 4 significantly contributes to Alba’s efforts to reduce Greenhouse Gas (GHG) emissions, aligning with Bahrain’s Net Zero 2060 objectives and Alba’s ESG Roadmap.

Execution
Project Management and Execution
  • Alba’s core team, in collaboration with ESBI International, managed the project.
  • Main contractors included SEPCOIII Bahrain Construction Company (lead), Tiejun International DMCC, and Mitsubishi Power Limited, with engagement of local subcontractors.
  • The Project was completed one month ahead of schedule, within budget, and maintained exceptional safety standards.
Key Facts
KEY FACTS
BLOCK 4 CAPACITY
Block Capacity

680.9

MW
SAFETY PERFORMANCE
Safety Performance

1 Million

Hours without LTI
COMBINED CYCLE EFFICIENCY RATE
Cycle Efficiency
+

60%

One of the highest in the industry
TRAINING HOURS FOR ALBA EMPLOYEES
Training Hours

+8,000

Hours
Key Milestone
KEY MILESTONES
Coco leaves
16 May, 2022
EPC Agreement signed with Mitsubishi Power & SEPCOIII
Coco leaves
14 November 2022
Securing Financial Close
Coco leaves
16 October 2023
Arrival of M701JAC Gas Turbine
Coco leaves
22 December 2024
Commercial Operation Commencement, 1-Month before Schedule
Coco leaves
26 September 2022
First Concrete Pour
Coco leaves
20 March 2023
Procurement & Foundation Works Completed
Coco leaves
23 April 2024
First Fire of the Gas Turbine
Key Development
KEY FACTS
Post Block 4 commissioning
Key Facts

Total Capacity of Power Stations

+4,200

MW

at 25 °c
Key Facts

GHG emissions intensity ratio to be reduced by

0.5

Tonnes of CO2

per one tonne of aluminium produced